Arabian Ranches III - Joy construction photos

98 photos from 10 site inspections, newest first. The percentage is how much of Arabian Ranches III - Joy was built on the day of each visit.

9 February 2023100% built

24 January 202398% built

23 August 202290% built

12 May 202280% built

25 January 202265% built

29 September 202142% built

14 April 202121% built

24 December 202013% built

22 January 20201.8% built

2 October 20191.0% built

Back to Arabian Ranches III - Joy construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.