Seventh Heaven - Ashjar construction photos

158 photos from 17 site inspections, newest first. The percentage is how much of Seventh Heaven - Ashjar was built on the day of each visit.

19 August 2022100% built

27 January 202296% built

13 October 202194% built

14 June 202193% built

17 January 202192% built

25 September 201993% built

1 July 201992% built

2 January 201989% built

5 November 201888% built

15 May 201885% built

21 January 201878% built

5 February 201770% built

5 June 201660% built

25 October 201533% built

23 June 201516% built

6 April 201514% built

15 January 201512% built

Back to Seventh Heaven - Ashjar construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.