Albarari Ixora Villas construction photos
38 photos from 6 site inspections, newest first. The percentage is how much of Albarari Ixora Villas was built on the day of each visit.
9 October 2025100% built
4 June 202588% built
26 September 202464% built
3 May 202426% built
15 February 202414% built
17 August 20232.2% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.