Marsa Al Arab Villas construction photos

94 photos from 11 site inspections, newest first. The percentage is how much of Marsa Al Arab Villas was built on the day of each visit.

12 June 2023100% built

2 February 202397% built

31 August 202271% built

29 March 202250% built

7 February 202244% built

26 August 202124% built

21 March 202113% built

5 November 20209.8% built

20 July 20206.2% built

8 March 20204.8% built

24 October 20190.3% built