57 photos from 9 site inspections, newest first. The percentage is how much of Town Square Hayat was built on the day of each visit.

24 June 2018100% built

19 February 201886% built

20 November 201780% built

8 August 201773% built

12 July 201769% built

8 March 201756% built

16 November 201635% built

24 July 201616% built

1 October 20153.0% built

Back to Town Square Hayat construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.