The Regent construction photos

39 photos from 7 site inspections, newest first. The percentage is how much of The Regent was built on the day of each visit.

26 May 2025100% built

13 March 202573% built

4 September 202429% built

7 June 202415% built

26 March 20248.6% built

14 August 20230% built

29 November 20220% built

Back to The Regent construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.