Sama Townhouses construction photos
67 photos from 7 site inspections, newest first. The percentage is how much of Sama Townhouses was built on the day of each visit.
15 September 2021100% built
7 December 202074% built
6 August 202061% built
22 April 202045% built
25 December 201925% built
25 August 201912% built
8 April 20192.6% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.