30 photos from 6 site inspections, newest first. The percentage is how much of Ora was built on the day of each visit.

30 April 202647% built

9 January 202636% built

19 September 202522% built

24 April 202514% built

24 January 20253.8% built

8 March 20240% built

Back to Ora construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.