Noor Townhouses construction photos
122 photos from 13 site inspections, newest first. The percentage is how much of Noor Townhouses was built on the day of each visit.
21 September 2020100% built
4 June 202097% built
2 June 202097% built
20 May 202097% built
24 March 202092% built
22 March 202092% built
14 October 201972% built
28 May 201950% built
4 April 201943% built
23 January 201930% built
23 September 201820% built
4 April 201814% built
8 October 201710% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.