The Villa 3 construction progress

The register lists The Villa 3 in The Villa as complete, with a registered completion date of June 2023. Its last site inspection on record was in June 2023. The developer is Dubai Land Residences.

100%

Built, at the site inspection of 2 June 2023

Construction complete

Registered completion date
June 2023
Construction started
November 2008
First registered
October 2010
Developer
Dubai Land Residences
Community
The Villa
Units
14
Escrow bank
Mashreq Bank
Name in Arabic
الفيلا 3
Project number
1296
Site inspections
5

Schedule

The register lists The Villa 3 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20092012201520182021
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

2 June 2023

100%+13 pts

  • The Villa 3 construction site, inspection photo 1, 2 June 2023
  • The Villa 3 construction site, inspection photo 2, 2 June 2023
  • The Villa 3 construction site, inspection photo 3, 2 June 2023
  • The Villa 3 construction site, inspection photo 4, 2 June 2023

1 February 2022

87%+6.0 pts

  • The Villa 3 construction site, inspection photo 1, 1 February 2022
  • The Villa 3 construction site, inspection photo 2, 1 February 2022
  • The Villa 3 construction site, inspection photo 3, 1 February 2022
  • The Villa 3 construction site, inspection photo 4, 1 February 2022

17 September 2014

82%+52 pts

  • The Villa 3 construction site, inspection photo 1, 17 September 2014
  • The Villa 3 construction site, inspection photo 2, 17 September 2014
  • The Villa 3 construction site, inspection photo 3, 17 September 2014
  • The Villa 3 construction site, inspection photo 4, 17 September 2014

4 June 2013

30%+0.9 pts

  • The Villa 3 construction site, inspection photo 1, 4 June 2013
  • The Villa 3 construction site, inspection photo 2, 4 June 2013
  • The Villa 3 construction site, inspection photo 3, 4 June 2013
  • The Villa 3 construction site, inspection photo 4, 4 June 2013

12 December 2012

29%

  • The Villa 3 construction site, inspection photo 1, 12 December 2012
  • The Villa 3 construction site, inspection photo 2, 12 December 2012
  • The Villa 3 construction site, inspection photo 3, 12 December 2012
  • The Villa 3 construction site, inspection photo 4, 12 December 2012

All 38 site photos, by inspection date

Context

Own a unit in The Villa 3?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the The Villa 3 handover date?
Construction of The Villa 3 is recorded as complete, with a registered completion date of June 2023. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on The Villa 3?
The Villa 3 was 100% built at the site inspection on 2 June 2023. The site has been inspected 5 times since December 2012. The Land Department took 38 site photos at its inspections.
Is The Villa 3 delayed?
The register lists construction as complete.
Who is building The Villa 3?
The registered developer is Dubai Land Residences.
Which bank holds the escrow account for The Villa 3?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.