The Onyx construction photos

97 photos from 10 site inspections, newest first. The percentage is how much of The Onyx was built on the day of each visit.

26 December 2016100% built

22 June 201697% built

8 March 201695% built

30 November 201591% built

6 August 201584% built

16 February 201567% built

6 November 201442% built

17 June 201431% built

1 February 201427% built

17 August 201319% built

Back to The Onyx construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.