Sobha Hartland Greens - Phase III construction photos

83 photos from 9 site inspections, newest first. The percentage is how much of Sobha Hartland Greens - Phase III was built on the day of each visit.

11 January 2021100% built

22 November 202095% built

24 February 202090% built

9 September 201970% built

2 April 201943% built

5 November 201825% built

27 August 201817% built

8 May 20185.8% built

10 January 20181.3% built

Back to Sobha Hartland Greens - Phase III construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.