Sobha Hartland Greens- Phase I construction photos
82 photos from 10 site inspections, newest first. The percentage is how much of Sobha Hartland Greens- Phase I was built on the day of each visit.
18 September 2018100% built
8 July 201893% built
22 March 201876% built
6 December 201757% built
30 May 201736% built
22 March 201731% built
25 January 201722% built
14 November 201617% built
10 April 20168.2% built
23 August 20151.0% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.