Kensington Waters construction photos

53 photos from 7 site inspections, newest first. The percentage is how much of Kensington Waters was built on the day of each visit.

14 February 2025100% built

10 July 202482% built

24 April 202472% built

14 September 202338% built

11 May 202322% built

2 January 20238.4% built

21 June 20222.9% built

Back to Kensington Waters construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.