Gemini Splendor construction photos

66 photos from 7 site inspections, newest first. The percentage is how much of Gemini Splendor was built on the day of each visit.

7 October 2018100% built

24 January 201880% built

12 November 201767% built

17 August 201751% built

1 May 201738% built

25 January 201724% built

17 November 201615% built

Back to Gemini Splendor construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.