Berkeley Place construction photos

56 photos from 6 site inspections, newest first. The percentage is how much of Berkeley Place was built on the day of each visit.

24 December 2024100% built

9 July 202484% built

20 March 202462% built

14 September 202334% built

11 May 202317% built

2 January 20236.9% built

Back to Berkeley Place construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.