Remraam - Al Ramth construction progress

The register lists Remraam - Al Ramth in Remraam as complete, with a registered completion date of December 2021. Its last site inspection on record was in December 2021. The developer is Remraam.

100%

Built, at the site inspection of 16 December 2021

Construction complete

Registered completion date
December 2021
Construction started
October 2017
First registered
August 2017
Developer
Remraam
Community
Remraam
Units
1,392
Escrow bank
Dubai Islamic Bank
Name in Arabic
رمرام - الرمث
Project number
1924
Site inspections
7

Schedule

The register lists Remraam - Al Ramth as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2018201920202021
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

16 December 2021

100%+1.9 pts

  • Remraam - Al Ramth construction site, inspection photo 1, 16 December 2021
  • Remraam - Al Ramth construction site, inspection photo 2, 16 December 2021
  • Remraam - Al Ramth construction site, inspection photo 3, 16 December 2021
  • Remraam - Al Ramth construction site, inspection photo 4, 16 December 2021

1 April 2021

98%+1.1 pts

  • Remraam - Al Ramth construction site, inspection photo 1, 1 April 2021
  • Remraam - Al Ramth construction site, inspection photo 2, 1 April 2021
  • Remraam - Al Ramth construction site, inspection photo 3, 1 April 2021
  • Remraam - Al Ramth construction site, inspection photo 4, 1 April 2021

16 September 2020

97%+16 pts

  • Remraam - Al Ramth construction site, inspection photo 1, 16 September 2020
  • Remraam - Al Ramth construction site, inspection photo 2, 16 September 2020
  • Remraam - Al Ramth construction site, inspection photo 3, 16 September 2020
  • Remraam - Al Ramth construction site, inspection photo 4, 16 September 2020

25 December 2019

81%+31 pts

  • Remraam - Al Ramth construction site, inspection photo 1, 25 December 2019
  • Remraam - Al Ramth construction site, inspection photo 2, 25 December 2019
  • Remraam - Al Ramth construction site, inspection photo 3, 25 December 2019
  • Remraam - Al Ramth construction site, inspection photo 4, 25 December 2019

5 August 2019

50%+22 pts

  • Remraam - Al Ramth construction site, inspection photo 1, 5 August 2019
  • Remraam - Al Ramth construction site, inspection photo 2, 5 August 2019
  • Remraam - Al Ramth construction site, inspection photo 3, 5 August 2019
  • Remraam - Al Ramth construction site, inspection photo 4, 5 August 2019

19 February 2019

28%+23 pts

  • Remraam - Al Ramth construction site, inspection photo 1, 19 February 2019
  • Remraam - Al Ramth construction site, inspection photo 2, 19 February 2019
  • Remraam - Al Ramth construction site, inspection photo 3, 19 February 2019
  • Remraam - Al Ramth construction site, inspection photo 4, 19 February 2019

14 August 2018

5.3%

  • Remraam - Al Ramth construction site, inspection photo 1, 14 August 2018
  • Remraam - Al Ramth construction site, inspection photo 2, 14 August 2018
  • Remraam - Al Ramth construction site, inspection photo 3, 14 August 2018
  • Remraam - Al Ramth construction site, inspection photo 4, 14 August 2018

All 74 site photos, by inspection date

Own a unit in Remraam - Al Ramth?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Remraam - Al Ramth handover date?
Construction of Remraam - Al Ramth is recorded as complete, with a registered completion date of December 2021. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Remraam - Al Ramth?
Remraam - Al Ramth was 100% built at the site inspection on 16 December 2021. The site has been inspected 7 times since August 2018. The Land Department took 74 site photos at its inspections.
Is Remraam - Al Ramth delayed?
The register lists construction as complete.
Who is building Remraam - Al Ramth?
The registered developer is Remraam.
Which bank holds the escrow account for Remraam - Al Ramth?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.