Nb Residences construction progress

The register lists Nb Residences in Pearl Jumeira as complete, with a registered completion date of August 2017. Its last site inspection on record was in December 2017. The developer is Pj Hotel Residential.

100%

Built, at the site inspection of 5 December 2017

Construction complete

Registered completion date
August 2017
Construction started
July 2014
First registered
February 2016
Developer
Pj Hotel Residential
Community
Pearl Jumeira
Units
65
Escrow bank
Dubai Islamic Bank
Name in Arabic
ان بي ريزيدنسس
Project number
1724
Site inspections
3

Schedule

The register lists Nb Residences as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%201520162017
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

5 December 2017

100%+0.9 pts

  • Nb Residences construction site, inspection photo 1, 5 December 2017
  • Nb Residences construction site, inspection photo 2, 5 December 2017
  • Nb Residences construction site, inspection photo 3, 5 December 2017
  • Nb Residences construction site, inspection photo 4, 5 December 2017

25 July 2017

99%+4.4 pts

  • Nb Residences construction site, inspection photo 1, 25 July 2017
  • Nb Residences construction site, inspection photo 2, 25 July 2017
  • Nb Residences construction site, inspection photo 3, 25 July 2017
  • Nb Residences construction site, inspection photo 4, 25 July 2017

20 March 2017

95%

  • Nb Residences construction site, inspection photo 1, 20 March 2017
  • Nb Residences construction site, inspection photo 2, 20 March 2017
  • Nb Residences construction site, inspection photo 3, 20 March 2017
  • Nb Residences construction site, inspection photo 4, 20 March 2017

All 37 site photos, by inspection date

Own a unit in Nb Residences?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Nb Residences handover date?
Construction of Nb Residences is recorded as complete, with a registered completion date of August 2017. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Nb Residences?
Nb Residences was 100% built at the site inspection on 5 December 2017. The site has been inspected 3 times since March 2017. The Land Department took 37 site photos at its inspections.
Is Nb Residences delayed?
The register lists construction as complete.
Who is building Nb Residences?
The registered developer is Pj Hotel Residential.
Which bank holds the escrow account for Nb Residences?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.