The Royal Atlantis,Resort And Residences construction photos

179 photos from 17 site inspections, newest first. The percentage is how much of The Royal Atlantis,Resort And Residences was built on the day of each visit.

1 February 2023100% built

7 November 202294% built

30 June 202292% built

3 February 202287% built

24 November 202185% built

9 August 202181% built

9 February 202175% built

27 October 202070% built

7 July 202065% built

3 February 202057% built

3 September 201950% built

28 April 201942% built

10 January 201935% built

18 October 201830% built

26 June 201823% built

27 February 201818% built

6 February 20175.1% built

Back to The Royal Atlantis,Resort And Residences construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.