Serenia Residences The Palm construction photos
52 photos from 7 site inspections, newest first. The percentage is how much of Serenia Residences The Palm was built on the day of each visit.
25 February 2018100% built
20 August 201782% built
9 April 201762% built
2 November 201640% built
2 June 201621% built
23 February 201612% built
4 October 201510% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.