Serenia Living construction photos

100 photos from 12 site inspections, newest first. The percentage is how much of Serenia Living was built on the day of each visit.

23 April 2026100% built

31 March 202698% built

26 January 202696% built

1 October 202591% built

26 May 202580% built

5 February 202562% built

17 October 202443% built

7 June 202431% built

30 January 202410% built

7 November 20237.6% built

5 June 20235.5% built

21 February 20233.8% built

Back to Serenia Living construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.