Palme Couture construction photos

64 photos from 7 site inspections, newest first. The percentage is how much of Palme Couture was built on the day of each visit.

26 March 2018100% built

24 January 201898% built

20 September 201787% built

19 February 201775% built

20 June 201648% built

20 December 201531% built

3 March 20157.5% built

Back to Palme Couture construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.