Club Villas construction photos

70 photos from 6 site inspections, newest first. The percentage is how much of Club Villas was built on the day of each visit.

30 April 2019100% built

3 April 201996% built

23 October 201890% built

4 March 201887% built

18 September 201780% built

5 December 201640% built

Back to Club Villas construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.