Palm Jebel Ali - Frond N construction photos
56 photos taken by Dubai Land Department engineers at 8 site inspections, newest first. The percentage is how much of Palm Jebel Ali - Frond N was built on the day of each visit.
5 August 202647% built
30 April 202635% built
27 January 202624% built
23 October 202513% built
23 July 20256.0% built
29 March 20252.1% built
11 November 20240.1% built
2 March 20230% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.