Nad Al Sheba Gardens Phase 8 & 9 construction progress
The registered completion date for Nad Al Sheba Gardens Phase 8 & 9 in Nad Al Shiba First is October 2028. At the last site inspection, in August 2026, it was 0.7% built. The developer is Nas Estates.
0.7%
Built, at the site inspection of 20 August 2026
Running behind its date
- Registered completion date
- October 2028
- Finish at recent pace
- March 2138
- Construction started
- September 2025
- First registered
- July 2025
- Developer
- Nas Estates
- Community
- Nad Al Shiba First
- Units
- 201
- Escrow bank
- Emirates NBD
- Name in Arabic
- ند الشبا جاردنز المرحلة 8 & 9
- Project number
- 3860
- Site inspections
- 4
Schedule
Between February 2026 and August 2026 the site added about 0.1 points a month. At that rate it would finish around March 2138, more than three months after its registered date of October 2028.
Site inspections
20 August 2026
0.7%+0.1 pts
14 May 2026
0.6%+0.4 pts
4 February 2026
0.2%+0.2 pts
1 July 2025
0%
Context
Nad Al Shiba First has 3 projects under construction, 2.8% built on average.
Nas Estates has 8 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Nad Al Sheba Gardens Phase 8 & 9?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Nad Al Sheba Gardens Phase 8 & 9 handover date?
- The registered completion date is October 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around March 2138. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Nad Al Sheba Gardens Phase 8 & 9?
- Nad Al Sheba Gardens Phase 8 & 9 was 0.7% built at the site inspection on 20 August 2026. The site has been inspected 4 times since July 2025. The Land Department took 12 site photos at its inspections.
- Is Nad Al Sheba Gardens Phase 8 & 9 delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of October 2028.
- Who is building Nad Al Sheba Gardens Phase 8 & 9?
- The registered developer is Nas Estates. It has 7 other projects under construction in Dubai.
- Which bank holds the escrow account for Nad Al Sheba Gardens Phase 8 & 9?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Nad Al Sheba Gardens Phase 4Also by Nas Estates. 76%.
- Nad Al Sheba Gardens Phase 5Also by Nas Estates. 38%.
- Nad Al Sheba Gardens Phase 6Also by Nas Estates. 14%.
- Nad Al Sheba Gardens Phase 7Also by Nas Estates. 7.5%, Due February 2028.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.png&w=3840&q=75)
.png&w=3840&q=75)
.png&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)