Nad Al Sheba Gardens Phase 8 & 9 construction progress

Nad Al Sheba Gardens Phase 8 & 9 in Nad Al Shiba First is 0.7% built at the Land Department inspection of August 2026. Developer Nas Estates. Completion registered for October 2028.

0.7%

Built, at the Land Department site inspection of 20 August 2026

Running behind its date

Completion date (Land Department)
October 2028
Finish at recent pace
March 2138
Construction started
September 2025
Registered with the Land Department
July 2025
Developer
Nas Estates
Units
201
Escrow bank
Emirates NBD
Name in Arabic
ند الشبا جاردنز المرحلة 8 & 9
Land Department project number
3860
Land Department site inspections
4

Schedule

Between February 2026 and August 2026 the site added about 0.1 points a month. At that rate it would finish around March 2138, more than three months after the October 2028 date registered with the Land Department.

0%25%50%75%100%202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

20 August 2026

0.7%+0.1 pts

  • Nad Al Sheba Gardens Phase 8 & 9 construction site, Land Department inspection photo 1, 20 August 2026
  • Nad Al Sheba Gardens Phase 8 & 9 construction site, Land Department inspection photo 2, 20 August 2026
  • Nad Al Sheba Gardens Phase 8 & 9 construction site, Land Department inspection photo 3, 20 August 2026

14 May 2026

0.6%+0.4 pts

  • Nad Al Sheba Gardens Phase 8 & 9 construction site, Land Department inspection photo 1, 14 May 2026
  • Nad Al Sheba Gardens Phase 8 & 9 construction site, Land Department inspection photo 2, 14 May 2026
  • Nad Al Sheba Gardens Phase 8 & 9 construction site, Land Department inspection photo 3, 14 May 2026

4 February 2026

0.2%+0.2 pts

  • Nad Al Sheba Gardens Phase 8 & 9 construction site, Land Department inspection photo 1, 4 February 2026
  • Nad Al Sheba Gardens Phase 8 & 9 construction site, Land Department inspection photo 2, 4 February 2026
  • Nad Al Sheba Gardens Phase 8 & 9 construction site, Land Department inspection photo 3, 4 February 2026
  • Nad Al Sheba Gardens Phase 8 & 9 construction site, Land Department inspection photo 4, 4 February 2026

1 July 2025

0%

  • Nad Al Sheba Gardens Phase 8 & 9 construction site, Land Department inspection photo 1, 1 July 2025
  • Nad Al Sheba Gardens Phase 8 & 9 construction site, Land Department inspection photo 2, 1 July 2025

All 12 site photos, by inspection date

Context

Nad Al Shiba First has 3 projects under construction, 1.7% built on average.

Nas Estates has 8 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Nad Al Sheba Gardens Phase 8 & 9?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Nad Al Sheba Gardens Phase 8 & 9 be completed?
The completion date registered with the Dubai Land Department is October 2028. At the pace of its recent inspections the site would reach 100% around March 2138. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Nad Al Sheba Gardens Phase 8 & 9 is built?
0.7%, measured at the Land Department site inspection on 20 August 2026. The Land Department engineers have inspected the site 4 times since July 2025.
Is Nad Al Sheba Gardens Phase 8 & 9 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of October 2028.
Who is building Nad Al Sheba Gardens Phase 8 & 9?
The registered developer is Nas Estates. It has 7 other projects under construction in Dubai.
Which bank holds the escrow account for Nad Al Sheba Gardens Phase 8 & 9?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.