Nad Al Sheba Gardens Phase 6 construction photos

38 photos taken by Dubai Land Department engineers at 7 site inspections, newest first. The percentage is how much of Nad Al Sheba Gardens Phase 6 was built on the day of each visit.

16 July 202614% built

28 April 202611% built

22 January 20267.1% built

2 October 20251.3% built

10 June 20250.4% built

4 March 20250.2% built

1 May 20240% built

Back to Nad Al Sheba Gardens Phase 6 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.