101 photos from 13 site inspections, newest first. The percentage is how much of Mudon Phase 3 _ Neighbourhood I- Arabella was built on the day of each visit.

4 April 2019100% built

17 December 201895% built

12 November 201894% built

9 September 201891% built

27 March 201879% built

13 December 201770% built

14 June 201740% built

9 February 201720% built

11 January 201715% built

29 August 201610% built

28 April 20164.5% built

16 December 20153.0% built

3 September 20150% built

Back to Mudon Phase 3 _ Neighbourhood I- Arabella construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.