Mudon-Phase 2 construction progress

The register lists Mudon-Phase 2 in Mudon as complete, with a registered completion date of November 2015. Its last site inspection on record was in December 2016. The developer is Mdn Real Estate.

100%

Built, at the site inspection of 5 December 2016

Construction complete

Registered completion date
November 2015
Construction started
May 2014
First registered
May 2014
Developer
Mdn Real Estate
Community
Mudon
Units
405
Escrow bank
Mashreq Bank
Name in Arabic
مدن-المرحله الثانيه (2)
Project number
1521
Site inspections
6

Schedule

The register lists Mudon-Phase 2 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20152016
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

5 December 2016

100%+9.5 pts

  • Mudon-Phase 2 construction site, inspection photo 1, 5 December 2016
  • Mudon-Phase 2 construction site, inspection photo 2, 5 December 2016
  • Mudon-Phase 2 construction site, inspection photo 3, 5 December 2016
  • Mudon-Phase 2 construction site, inspection photo 4, 5 December 2016

29 August 2016

91%+13 pts

  • Mudon-Phase 2 construction site, inspection photo 1, 29 August 2016
  • Mudon-Phase 2 construction site, inspection photo 2, 29 August 2016
  • Mudon-Phase 2 construction site, inspection photo 3, 29 August 2016
  • Mudon-Phase 2 construction site, inspection photo 4, 29 August 2016

28 April 2016

78%+19 pts

  • Mudon-Phase 2 construction site, inspection photo 1, 28 April 2016
  • Mudon-Phase 2 construction site, inspection photo 2, 28 April 2016
  • Mudon-Phase 2 construction site, inspection photo 3, 28 April 2016
  • Mudon-Phase 2 construction site, inspection photo 4, 28 April 2016

16 December 2015

59%+14 pts

  • Mudon-Phase 2 construction site, inspection photo 1, 16 December 2015
  • Mudon-Phase 2 construction site, inspection photo 2, 16 December 2015
  • Mudon-Phase 2 construction site, inspection photo 3, 16 December 2015
  • Mudon-Phase 2 construction site, inspection photo 4, 16 December 2015

20 August 2015

44%+24 pts

  • Mudon-Phase 2 construction site, inspection photo 1, 20 August 2015
  • Mudon-Phase 2 construction site, inspection photo 2, 20 August 2015
  • Mudon-Phase 2 construction site, inspection photo 3, 20 August 2015
  • Mudon-Phase 2 construction site, inspection photo 4, 20 August 2015

5 February 2015

20%

  • Mudon-Phase 2 construction site, inspection photo 1, 5 February 2015
  • Mudon-Phase 2 construction site, inspection photo 2, 5 February 2015
  • Mudon-Phase 2 construction site, inspection photo 3, 5 February 2015
  • Mudon-Phase 2 construction site, inspection photo 4, 5 February 2015

All 46 site photos, by inspection date

Own a unit in Mudon-Phase 2?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Mudon-Phase 2 handover date?
Construction of Mudon-Phase 2 is recorded as complete, with a registered completion date of November 2015. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Mudon-Phase 2?
Mudon-Phase 2 was 100% built at the site inspection on 5 December 2016. The site has been inspected 6 times since February 2015. The Land Department took 46 site photos at its inspections.
Is Mudon-Phase 2 delayed?
The register lists construction as complete.
Who is building Mudon-Phase 2?
The registered developer is Mdn Real Estate.
Which bank holds the escrow account for Mudon-Phase 2?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.