Mudon-Phase 2 construction progress
The register lists Mudon-Phase 2 in Mudon as complete, with a registered completion date of November 2015. Its last site inspection on record was in December 2016. The developer is Mdn Real Estate.
100%
Built, at the site inspection of 5 December 2016
Construction complete
- Registered completion date
- November 2015
- Construction started
- May 2014
- First registered
- May 2014
- Developer
- Mdn Real Estate
- Community
- Mudon
- Units
- 405
- Escrow bank
- Mashreq Bank
- Name in Arabic
- مدن-المرحله الثانيه (2)
- Project number
- 1521
- Site inspections
- 6
Schedule
The register lists Mudon-Phase 2 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.
Site inspections
5 December 2016
100%+9.5 pts
29 August 2016
91%+13 pts
28 April 2016
78%+19 pts
16 December 2015
59%+14 pts
20 August 2015
44%+24 pts
5 February 2015
20%
Own a unit in Mudon-Phase 2?
The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.
Notify me when it launchesQuestions
- When is the Mudon-Phase 2 handover date?
- Construction of Mudon-Phase 2 is recorded as complete, with a registered completion date of November 2015. Handover of individual units follows on the developer's schedule, which the register does not show.
- What is the latest construction update on Mudon-Phase 2?
- Mudon-Phase 2 was 100% built at the site inspection on 5 December 2016. The site has been inspected 6 times since February 2015. The Land Department took 46 site photos at its inspections.
- Is Mudon-Phase 2 delayed?
- The register lists construction as complete.
- Who is building Mudon-Phase 2?
- The registered developer is Mdn Real Estate.
- Which bank holds the escrow account for Mudon-Phase 2?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.