Mudon Al Ranim 8 construction progress
The register lists Mudon Al Ranim 8 in Mudon as complete, with a registered completion date of September 2026. Its last site inspection on record was in September 2026. The developer is Mdn Real Estate.
100%
Built, at the site inspection of 15 September 2026
Construction complete
- Registered completion date
- September 2026
- Construction started
- September 2023
- First registered
- June 2023
- Developer
- Mdn Real Estate
- Community
- Mudon
- Units
- 228
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- مدن الرنيم 8
- Project number
- 2701
- Site inspections
- 10
Schedule
The register lists Mudon Al Ranim 8 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.
Site inspections
15 September 2026
100%+8.0 pts
4 May 2026
92%+11 pts
27 January 2026
81%+22 pts
30 October 2025
59%+16 pts
1 August 2025
43%+18 pts
1 May 2025
26%+14 pts
20 January 2025
12%+11 pts
24 September 2024
1.3%+0.9 pts
16 May 2024
0.5%+0.5 pts
14 June 2023
0%
Own a unit in Mudon Al Ranim 8?
The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.
Notify me when it launchesQuestions
- When is the Mudon Al Ranim 8 handover date?
- Construction of Mudon Al Ranim 8 is recorded as complete, with a registered completion date of September 2026. Handover of individual units follows on the developer's schedule, which the register does not show.
- What is the latest construction update on Mudon Al Ranim 8?
- Mudon Al Ranim 8 was 100% built at the site inspection on 15 September 2026. The site has been inspected 10 times since June 2023. The Land Department took 89 site photos at its inspections.
- Is Mudon Al Ranim 8 delayed?
- The register lists construction as complete.
- Who is building Mudon Al Ranim 8?
- The registered developer is Mdn Real Estate.
- Which bank holds the escrow account for Mudon Al Ranim 8?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.