Mudon Al Ranim 6 construction photos

66 photos from 9 site inspections, newest first. The percentage is how much of Mudon Al Ranim 6 was built on the day of each visit.

15 July 2026100% built

31 January 202685% built

30 October 202577% built

1 August 202561% built

1 May 202544% built

20 January 202522% built

24 September 20245.1% built

1 May 20242.0% built

3 May 20230% built

Back to Mudon Al Ranim 6 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.