Mudon Al Ranim 4 construction photos
70 photos from 9 site inspections, newest first. The percentage is how much of Mudon Al Ranim 4 was built on the day of each visit.
15 January 2026100% built
31 October 202598% built
1 August 202590% built
1 May 202585% built
20 January 202561% built
24 September 202436% built
6 March 202414% built
19 September 20231.4% built
11 January 20230% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.