The Fields At D11 - Mbrmc construction photos

273 photos from 28 site inspections, newest first. The percentage is how much of The Fields At D11 - Mbrmc was built on the day of each visit.

6 April 2026100% built

10 November 202599% built

11 June 202598% built

18 November 202496% built

1 May 202493% built

27 November 202389% built

20 June 202378% built

17 January 202375% built

17 October 202271% built

24 June 202266% built

6 June 202265% built

25 January 202262% built

12 October 202156% built

22 June 202154% built

10 March 202153% built

19 October 202050% built

13 February 202047% built

16 December 201946% built

23 April 201943% built

4 December 201843% built

23 July 201838% built

10 April 201835% built

17 January 201830% built

17 September 201720% built

25 May 20175.7% built

7 March 20175.0% built

8 December 20161.5% built

27 August 20150% built

Back to The Fields At D11 - Mbrmc construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.