Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 27 construction photos
52 photos from 6 site inspections, newest first. The percentage is how much of Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 27 was built on the day of each visit.
28 July 2023100% built
14 June 202398% built
12 January 202364% built
10 October 202237% built
20 June 202221% built
2 February 20224.7% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.