Skip to content

Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 25 construction photos

51 photos from 6 site inspections, newest first. The percentage is how much of Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 25 was built on the day of each visit.

28 July 2023100% built

13 June 202398% built

12 January 202365% built

7 October 202238% built

21 June 202223% built

2 February 20225.5% built

Back to Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 25 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.