Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 16 construction photos

102 photos from 11 site inspections, newest first. The percentage is how much of Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 16 was built on the day of each visit.

12 January 2023100% built

4 October 202291% built

15 June 202277% built

7 December 202170% built

9 December 202070% built

25 June 202063% built

8 April 202054% built

26 December 201944% built

20 October 201932% built

15 January 201910% built

8 August 20180.8% built

Back to Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 16 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.