Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 13 construction photos

71 photos from 8 site inspections, newest first. The percentage is how much of Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 13 was built on the day of each visit.

31 August 2023100% built

12 April 202374% built

4 January 202351% built

4 October 202236% built

15 June 202226% built

6 December 202110% built

8 December 202010% built

10 June 20203.5% built

Back to Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 13 construction progress