Bayline construction photos

42 photos from 7 site inspections, newest first. The percentage is how much of Bayline was built on the day of each visit.

19 July 202661% built

17 March 202642% built

14 November 202529% built

11 July 202511% built

24 February 20256.8% built

28 May 20240.1% built

10 October 20230% built

Back to Bayline construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.