Azizi Park Avenue construction photos

34 photos from 5 site inspections, newest first. The percentage is how much of Azizi Park Avenue was built on the day of each visit.

18 January 2024100% built

29 March 202375% built

4 April 202223% built

28 September 20215.3% built

18 February 20211.1% built

Back to Azizi Park Avenue construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.