Sobha Hartland Villas-Phase 1 construction photos
77 photos from 10 site inspections, newest first. The percentage is how much of Sobha Hartland Villas-Phase 1 was built on the day of each visit.
4 February 2020100% built
18 July 201995% built
2 April 201991% built
11 October 201881% built
22 March 201861% built
18 December 201747% built
17 August 201730% built
18 June 201720% built
23 March 201714% built
11 April 20163.1% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.