Sobha Hartland Villas-Phase 1 construction photos

77 photos from 10 site inspections, newest first. The percentage is how much of Sobha Hartland Villas-Phase 1 was built on the day of each visit.

4 February 2020100% built

18 July 201995% built

2 April 201991% built

11 October 201881% built

22 March 201861% built

18 December 201747% built

17 August 201730% built

18 June 201720% built

23 March 201714% built

11 April 20163.1% built

Back to Sobha Hartland Villas-Phase 1 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.