Azizi Riviera 9 construction photos

102 photos from 10 site inspections, newest first. The percentage is how much of Azizi Riviera 9 was built on the day of each visit.

22 June 2023100% built

7 April 202285% built

14 October 202180% built

6 April 202171% built

10 November 202064% built

14 July 202059% built

2 February 202047% built

27 May 201931% built

2 September 201820% built

9 August 201814% built

Back to Azizi Riviera 9 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.