Azizi Riviera 7 construction photos

91 photos from 10 site inspections, newest first. The percentage is how much of Azizi Riviera 7 was built on the day of each visit.

23 August 2022100% built

17 November 202182% built

23 June 202168% built

27 January 202161% built

17 June 202051% built

10 February 202046% built

9 July 201931% built

1 October 201820% built

2 September 201818% built

7 August 201814% built

Back to Azizi Riviera 7 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.