Azizi Riviera 45 construction photos

51 photos from 6 site inspections, newest first. The percentage is how much of Azizi Riviera 45 was built on the day of each visit.

18 January 2024100% built

25 September 202397% built

27 March 202383% built

27 October 202261% built

28 April 202242% built

20 September 202133% built

Back to Azizi Riviera 45 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.