Azizi Riviera 40 construction photos

53 photos from 7 site inspections, newest first. The percentage is how much of Azizi Riviera 40 was built on the day of each visit.

16 May 2024100% built

17 August 202271% built

12 January 202250% built

27 October 202141% built

24 December 202018% built

10 February 202015% built

21 August 201913% built

Back to Azizi Riviera 40 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.