Azizi Riviera 37 construction photos

67 photos from 8 site inspections, newest first. The percentage is how much of Azizi Riviera 37 was built on the day of each visit.

4 March 2024100% built

20 October 202278% built

3 February 202262% built

30 August 202157% built

23 May 202152% built

22 December 202030% built

23 December 201920% built

21 August 201915% built

Back to Azizi Riviera 37 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.