Azizi Riviera 34 construction photos

95 photos from 11 site inspections, newest first. The percentage is how much of Azizi Riviera 34 was built on the day of each visit.

14 September 2023100% built

21 July 202277% built

5 December 202161% built

14 June 202152% built

19 January 202146% built

7 September 202042% built

4 March 202031% built

13 February 202030% built

5 September 201921% built

8 January 201921% built

7 August 201821% built

Back to Azizi Riviera 34 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.