Azizi Riviera 28 construction photos

111 photos from 11 site inspections, newest first. The percentage is how much of Azizi Riviera 28 was built on the day of each visit.

12 September 2023100% built

12 October 202293% built

21 April 202276% built

2 November 202167% built

24 June 202151% built

21 January 202142% built

18 June 202025% built

6 February 202020% built

1 July 201920% built

7 May 201918% built

10 April 201918% built

Back to Azizi Riviera 28 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.