Azizi Riviera 22 construction photos

80 photos from 10 site inspections, newest first. The percentage is how much of Azizi Riviera 22 was built on the day of each visit.

17 October 2023100% built

11 April 202276% built

27 October 202168% built

30 March 202144% built

7 September 202033% built

2 February 202020% built

9 December 201911% built

4 September 201910% built

8 January 201910% built

9 August 20188.1% built

Back to Azizi Riviera 22 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.