Azizi Riviera 2 construction photos

119 photos from 13 site inspections, newest first. The percentage is how much of Azizi Riviera 2 was built on the day of each visit.

3 May 2023100% built

29 November 202298% built

21 February 202281% built

12 October 202172% built

29 March 202157% built

1 October 202051% built

17 February 202035% built

22 October 201922% built

9 July 201918% built

17 March 201914% built

3 January 201914% built

7 August 201811% built

3 April 20184.0% built

Back to Azizi Riviera 2 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.