Qpoint Liwan-Plot R082 construction photos
168 photos from 19 site inspections, newest first. The percentage is how much of Qpoint Liwan-Plot R082 was built on the day of each visit.
30 September 2018100% built
25 July 201899% built
15 April 201899% built
20 December 201798% built
9 October 201796% built
20 July 201795% built
6 March 201773% built
13 October 201668% built
29 May 201668% built
23 February 201668% built
2 November 201566% built
15 June 201560% built
2 February 201554% built
28 October 201449% built
16 July 201447% built
17 March 201447% built
17 June 201346% built
25 January 201339% built
9 September 201232% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.