Qpoint Liwan-Plot R051 construction photos

78 photos from 11 site inspections, newest first. The percentage is how much of Qpoint Liwan-Plot R051 was built on the day of each visit.

6 March 2017100% built

12 October 201676% built

26 May 201660% built

23 February 201649% built

25 October 201547% built

30 June 201545% built

18 February 201540% built

6 November 201434% built

16 July 201427% built

17 March 201421% built

27 June 201221% built

Back to Qpoint Liwan-Plot R051 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.